Item Coversheet
Brunswick County Board of Commissioners
ACTION AGENDA ITEM
December 4, 2017

Action Item # X. - 4.

From:
John Nichols, P.E.

Utilities - Wells Brothers Final Adjusting Change Order No. 1 and Agreement with Town of Boiling Spring Lakes (John Nichols, Director of Public Utilities)

Issue/Action Requested:

Request that the Board of Commissioners approve Final Adjusting Change Order No. 1 with Wells Brothers Construction for the 2016 Enterprise Funded Sewer Extension Project increasing the contract from $770,499.50 to $792,251.62 for an increase of $22,252.12 and approve an agreement with the Town of Boiling Spring Lakes providing compensation valued at $18,610 for street repaving. 

Background/Purpose of Request:

The construction contract change order reflects various additions and subtractions to unit price items as well as liquidated damages assessed to the contractor due to schedule noncompliance.  The majority of cost increases were due to an increase in depth of gravity sewer due to utility conflicts and pavement repairs on aging streets with minimal depth of pavement.  The agreement with the Town of Boiling Spring Lakes will provide $18,610 reimbursement to be used to cover a portion of the town’s repaving costs in lieu of patching pavement that is in great need of repair.  The pavement on the roads is nearing its life expectancy and a contribution to the repaving project was deemed more effective than repairing aged asphalt.

 

Staff recommends approval of Final Adjusting Change Order No. 1 with Wells Brothers Construction in the amount of $22,252.12 and approval of the agreement with the Town of Boiling Spring Lakes in the amount of $18,610.

Fiscal Impact:
Budget Amendment Required, Capital Project/Grant Ordinance Required, Pre-Audit Certification Required, Reviewed By Director of Fiscal Operations
Budget amendment and the associated CPO transfers $22,253 from the wastewater capital reserve undesignated funds to project for repairs.
Approved By County Attorney:
Yes
County Attorney's Recommendation:
Advisory Board Recommendation:
Not applicable
County Manager's Recommendation:
Recommend that the Board of Commissioners approve Final Adjusting Change Order No. 1 with Wells Brothers Construction for the 2016 Enterprise Funded Sewer Extension Project increasing the contract from $770,499.50 to $792,251.62 for an increase of $22,252.12 and approve an agreement with the Town of Boiling Spring Lakes providing compensation valued at $18,610 for street repaving. 
ATTACHMENTS:
Description
Utilities - 2016 Enterprise Funded Sewer Extension Final Adjusting Change Order No. 1 Wells Brothers - Attach 1
Utilities - Town of Boiling Spring Lakes Agreement - Attach 2
20171204 Budget Amendment Wells Brothers Change Order 1 Reserve.pdf
20171204 Budget Amendment Wells Brothers Change Order 1.pdf
20171204 CPO 2016 Enterprise Funded Main Extension.pdf